SCHEDULE OF PROJECT APPROVALS FROM JULY-SEPTEMBER 2015

In an effort to better track delivery of projects and programs for funding approval by the CIF committees and for project approval by the MDB, a quarterly Schedule of Project Approvals based on the latest MDB projections is posted the first week of each quarter. The schedule is subject to regular updates to reflect approval status.

PROJECTS FOR SC APPROVAL 
Amounts expressed in USD million

COUNTRY PROJECT TITLE MDB FUNDING PROJECTED COMMITTEE APPROVAL DATE REMARKS
Cambodia Climate resilience of rural infrastructure in Kampong Cham province as part of Rural Roads Improvement Project (RRIP-II) ADB         16.00 Jul-15 Submitted for committee approval on 4 September 2015
South Pacific-Papua New Guinea Building Climate Resilience in Papua New Guinea ADB         24.25 Jul-15  
Bolivia* Financial Risk Management for Climate Resilience in the Agriculture Sector IDB         10.00 Jul-15  
Cambodia* Rainwater Harvesting and Drip Irrigation for High-Value Crop Production in Cambodia ADB           5.00 Aug-15 Submitted for committee approval on 5 August, 2015; Approved on 8 September 2015
Mozambique Developing Climate Resilience in the Agricultural and Peri-Urban Water Sectors Through Provision of Credit Lines from Mozambican Banks-Investment Component IFC           5.00 Aug-15  
Mozambique Developing Community Climate Resilience Through Private Sector Engagement in Forest Management, Sustainbale Timber harvesting and/or tourism.  Options include forest areas in Niassa, Gorongosa and central Mozambique IFC           5.00 Aug-15  
Caribbean-Haiti* Support for the building of a climate resilient sorghum supply chain in Haiti IDB           3.00 Sep-15  
Caribbean-Saint Lucia* Supporting climate resilient investments in the agricultural sector in Saint Lucia: provision of small to medium sized loans to farmers, farmer associations, distributors/ wholesalers and processing companies. IDB           6.10 Sep-15  

Private Sector Set Aside Project
  Note: Updates are currently requested from the MDBs.Table will be updated once all submissions are received.

PROJECTS FOR MDB APPROVAL 
Amounts expressed in USD million

COUNTRY PROJECT TITLE MDB FUNDING PROJECTED MDB APPROVAL DATE REMARKS
Caribbean-Jamaica Improving Climate Data and Information Management IBRD           6.80 Jul-15  
Bangladesh Climate Smart SME Financing IFC         10.00 Aug-15  
Cambodia Rainwater Harvesting and Drip Irrigation for High-Value Crop Production in Cambodia ADB           5.00 Sep-15  
South Pacific-Papua New Guinea Building Climate Resilience in Papua New Guinea ADB         24.25 Sep-15  

* Private Sector Set Aside Projects
  Note: Updates are currently requested from the MDBs. Table will be updated once all submissions are received.

 

PROJECT APPROVALS FROM APRIL-JUNE 2015 (COMMITTEE)
Amounts expressed in USD million

COUNTRY PROJECT TITLE MDB FUNDING COMMITTEE APPROVAL DATE
Mozambique* Lurio Green Resources Forestry Project AfDB         11.00 Apr-15
Bangladesh Climate Smart SME Financing IFC         10.00 Apr-15
Mozambique Smallholder Irrigation Feasibility Project IFC           0.58 May-15
South Pacific-Regional Track Pacific Resilience Program IBRD           5.79 May-15
Caribbean-Jamaica Improving Climate Data and Information Management IBRD           6.80 May-15
Tajikistan Additional Financing to the Environmental Land Management and Rural Livelihoods IBRD           2.00 May-15
Cambodia Component 4-Cluster Technical Assistance:  Mainstreaming Climate Resilience into Development Planning of Key Vulnerable Sectors ADB           3.00 Jun-15
Caribbean-Jamaica* Financing water adaptation in Jamaica’s new urban housing sector IDB           5.75 Jun-15
Nepal Project 3:  Building Climate Resilient Communities Through Private Sector Participation-Expansion of Strengthening Vulnerable Infrastructure Project IFC         14.40 Jun-15

* Private Sector Set Aside Projects

PROJECT APPROVALS FROM APRIL-JUNE 2015 (MDB)
Amounts expressed in USD million

COUNTRY PROJECT TITLE MDB FUNDING MDB APPROVAL DATE
Caribbean-Regional Track Investment Proposal for the Caribbean Regional Track  IDB         10.39 May-15
Cambodia Component 3-Project 3-Flood-resilient Infratrusture Development in Sisopohon,Siem Reap, Kampong Thom, Battambang, Pursat and Kampong Cham ADB         10.00 Jun-15
Caribbean-Grenada Additional Financing to the Regional Disaster Vulnerability Reduction Project IBRD           8.80 Jun-15
South Pacific-Regional Track Pacific Resilience Program IBRD           5.79 Jun-15
Caribbean-Haiti Strengthening Hydromet Project IBRD           5.00 Jun-15
Tajikistan Additional Financing to the Environme